Solved: Microsoft project 2007 technical ?

Status
This thread has been Locked and is not open to further replies. Please start a New Thread if you're having a similar issue. View our Welcome Guide to learn how to use this site.

poppea

Thread Starter
Joined
Sep 21, 2004
Messages
76
Dear all,
I have included tasks in a project with theorethical starting dates.
Now if I go to tracking & I input the actual start, my bar representing the duration of my task on the GANTT chart will be shifted accordingly.

What i need to know is is there a way that i could see on my gantt chart both the original & actual bars one under the other so i can have a visual comparision of the shifting in my project after i correct by putting actual start values...

Thx
 

poppea

Thread Starter
Joined
Sep 21, 2004
Messages
76
after TOOLS - TRACKING - SAVE BASELINE - ENTIRE PROJECT,
a set of grey bars identical to the original planned bars should appear but they aren't.
Even after VIEW-TABLE:ENTRY-MORE TABLE-BASELINE (ensuring that task is selected), I am unable to view these grey baseline which could answer my question if resolved.
 

poppea

Thread Starter
Joined
Sep 21, 2004
Messages
76
ok, found it
the missing action was the following:
Right click on the Gantt chart - WIZARD -Baseline view...
 
Status
This thread has been Locked and is not open to further replies. Please start a New Thread if you're having a similar issue. View our Welcome Guide to learn how to use this site.

Users Who Are Viewing This Thread (Users: 0, Guests: 1)

As Seen On
As Seen On...

Welcome to Tech Support Guy!

Are you looking for the solution to your computer problem? Join our site today to ask your question. This site is completely free -- paid for by advertisers and donations.

If you're not already familiar with forums, watch our Welcome Guide to get started.

Join over 807,865 other people just like you!

Latest posts

Members online

Top